Kohl Elementary School 
View of the front of Kohl Elementary School 
 
Kohl Elementary School
1000 W 10th Avenue
Broomfield, CO  80020
720.561.8600
http://bvsd.org/schools/Kohl
Original construction date: 1959
Report Updated:  12/27/2011 
Project Details

Principal: Cindy Kaier

Project Manager:  Paul Wight

Architect: OZ Architecture

Contractor: Adolfson & Peterson

Original Project Budget:

 $3,986,949

Transfer from Program Reserve for asbestos 

+$250,000

Transfer from Program Reserve for utility upgrades

+$175,000

Return to Bond Program surplus

-$247,608

Revised Project Budget:  

$4,164,340

Kohl Elementary project expenditures

Budget Program expenditures

Design Advisory Team Members

Staff
Cindy Kaier, Principal
Tammi Simmons
Jackie Howard
Jeanne Powers
Cathy Brigham
George Hawk
Tami Attard

Parents
Stacy Klemp
Matthew Fite

Contact the Kohl DAT

DAT Meeting Schedule

2009
March 19; 3 p.m.
April 2, 16, 30; 3 p.m.
May 14; 3 p.m.
July TBD if necessary
September 3; 3 pm
October 29; 3 pm. ONLY if necessary

DAT Meeting Minutes

 

Project Timeline

Scheduled Milestones
uSD (schematic design) due 05/09; Complete
uDD (design development) drawings due 07/09; Complete
uCD (construction documents) due 09/09; Complete
uConstruction Scheduled 01/10 - 08/10; Complete

u= Design phase
u= Construction bidding
u= Construction phase

Project Status
Project is complete. All spaces are occupied.  
 
 
 
 
Construction photos - Jan/Feb. 2010
 

 

 

 

 

 

 

 

 

 

 

 

 

 
 
Construction photos - March 2010
 

 

 

 

 

 

 


Construction photos - June 2010

 

 

 

 

 

 

 

 


Construction Photos - July 2010

 
Resurfaced parking lot

 
New accessible parking and drop off

 
New entry vestibule

 
New flooring in classrooms


New window into remodeled
administrative suite 

 
Remodeled cafeteria

 

 

 

 

Project photos - August 2010

 
New entry and driveway

 

 
New rear entry vestibule and
awnings

 
New classroom addition

 

 
Clerestory in corridor

 
ADA accessibility ramps

 

 
New music addition

 


New science classroom

 


New science classroom

 

 
Tiles from old cafeteria were saved
and reinstalled


New cafeteria

 

 


Clerestory in new rear entry

 

Scope of Work

Facility Condition Assessment (FCA):

  • HVAC upgrades
  • Interior finishes upgraded (i.e. ceiling tiles, carpet, wall finishes, etc)
  • Roof replacement and repairs
  • Restroom renovations including ADA accessibility where required
  • Site irrigation system improvements
  • Interior signage program
  • Site paving replacement and repair

Program Compatibility Assessment (PCA):

  • Special Education improvements
  • Relocate art room
  • Provide small group instruction spaces
  • New cafeteria and kitchen facilities
  • New administrative offices and faculty workroom

Multi-Use Outdoor Facilities (MUOF):

  • Upgrade playground surfacing, equipment, and fencing
  • Provide adequate curbing and drainage
  • Replace aged and/or unsafe playground equipment
  • Make playgrounds ADA accessible

Information Technology (IT):

  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Implement VoIP to enhance communications capabilities and reduce costs